XYZ Reality has released a documentary about construction work at Applied Digital's Polaris Forge 1 AI Factory campus with contractor McGough. The film focuses on how the parties tracked progress and checked installation work during the live build.

It examines the use of real-time field verification on the multi-building data centre project in Ellendale, North Dakota, showing how the owner, contractor and technology provider shared progress data during construction and used it to monitor turnover milestones on a mission-critical site.

At the centre of the case study is a specific intervention during the Polaris Forge 1 build. McGough requested a proactive check of 12 generator room conduits before equipment placement, and XYZ Reality's field engineers found a two-foot offset from the 3D model that would have clashed with incoming day tanks.

According to the companies, the issue was corrected before concrete was poured. They said the check helped protect the turnover schedule and created a verification approach that could be repeated across similar generator rooms on the campus.

Early detection

The project offers a window into how contractors and owners are managing fast-tracked AI infrastructure programmes, where delays can be expensive and design or installation errors may not emerge until surrounding work is complete. Traditional inspection methods such as laser scanning and reality capture are often used retrospectively, meaning discrepancies may be identified only after concrete pours or adjacent services have already been installed.

XYZ Reality's approach involves field engineers bringing a coordinated 3D design model onto the active site using its Atom augmented reality hardhat. Checks are carried out against design intent with 3mm accuracy, and any emerging issues are logged alongside an assessment of their likely effect on the ready-for-service date.

That information is then used by both site teams and management. The same verified field data can be viewed at project and portfolio level, giving installation crews, project leaders and owners a shared picture of current progress and whether the delivery date remains achievable.

For McGough, the practical value was identifying errors early enough to avoid rework after later stages of installation. Keith Hardy, Senior Superintendent at McGough Construction, said the system also provided a more precise reading of schedule performance than visual inspection alone.

"XYZ's technology provides the precision that we need better than what the human eye can identify," said Keith Hardy, Senior Superintendent at McGough Construction. "We're able to be more honest with our schedule. XYZ's dashboard allowed us to really understand at any stage of the project, down to the tenth of a percentage point, how well we are tracking. Not only that, but it allowed our building owner to understand where we were in real time, and we were also able to convey that to our trade partners."

Installation checks

The conduit example became one of the main operating lessons highlighted in the documentary. The parties said standardising checks across repeated room layouts reduced the risk of the same error being replicated elsewhere on the site, while also giving management better information to adjust labour and materials planning.

Hardy contrasted that process with checks that take place only after installation. "The time the check took was unnoticeable compared to re-installing conduit that had been embedded wrong," he said. "Laser scanning after installation is already too late. Catching deviations before concrete and equipment go in allows us to apply lessons learned across every room with that same layout and verify installations at set-out."

AI infrastructure

The wider context is a surge in demand for AI infrastructure, which has put pressure on developers and contractors to deliver large-scale facilities on tight programmes. In that environment, owners are increasingly focused not only on build speed but also on how confidently teams can forecast completion and avoid slippage caused by late-stage clashes or rework.

XYZ Reality framed the Polaris Forge 1 experience as an example of closer coordination between parties working from a common data set. "The way we build today can't keep up with the pace these AI factories demand," said Anthony Canipa, Vice President of Client Operations at XYZ Reality. "Our job at XYZ is to bring predictability to everyone with a stake in the build: the builders, the developers, the hyperscalers and the investors behind them. We give teams the ability to be proactive and prevent the issues that cause massive, costly delays before they ever hit the schedule. What we saw at Polaris Forge 1 was excellent coordination between McGough and Applied Digital, because they were working from shared, trusted, verified and forward-looking information."